건축물 해체공사비 영향요인 및 실적공사비 분석 연구
- Author(s)
- 신동욱
- Issued Date
- 2019
- Keyword
- 해체공사비, 영향요인, 실적공사비, 기술통계분석
- Abstract
- The number of demolition work is rapidly increasing because the middle- and high-rised buildings constructed over the rapid industrialization and urbanization in the 1970s and 1980s have been deteriorated in social and structural aspects. The scale of the demolition industry is also expected to be expanded.
However, theoretical approaches or studies related to the demolition cost prediction are still insufficient. Most of the related studies are focused on calculating construction costs through the presentation and supplementation of the calculation standard of the building based on the standard quantity per unit. However, there is a disadvantage that the standard quantity per unit contains only the most common contents, which makes it difficult to reflect the characteristics of the demolition site. Other methods for calculating the cost of demolition work are to rely on experts having experience on similar projects or through comparative estimates of the technology holding company concerned. However, these methods have limitations in improving the accuracy and are lack of reliability.
Thus, as a basic research for reliable cost estimates, this study 1) derived important factors affecting the fluctuation of the building demolition costs and 2) performed an analysis of change in actual construction cost based on the site information. Based on literature reviews and experts’ group interview, the 14 factors affecting the demolition construction cost were extracted and the survey was conducted on the dismantling experts. The survey results indicated the importance and variation range of 14 factors on the cost of demolition work throughout the major processes of the demolition work (temporary work, structure demolition, and waste disposal) and the entire demolition work. After this, the site information of the completed demolition work was collected and comparative analysis was performed.
‘The 14 factors affecting the demolition construction cost’ derived from this study is meaningful as a basic study of the demolition cost that is insufficient at present. And it can be utilized as base data for the demolition work plan and budgeting by presenting the degree of impact and variation range of each factors on the main process and the overall process of the demolition work.
- Alternative Title
- Analysis on Cost Influencing Factors and Historical Cost Data of Building Demolition Work
- Alternative Author(s)
- Shin, Dong wook
- Affiliation
- 조선대학교 대학원
- Department
- 일반대학원 건축공학과
- Advisor
- 조규만, 김태훈
- Awarded Date
- 2019-02
- Table Of Contents
- ABSTRACT
제 1장 서 론 1
1.1 연구의 배경 및 목적 1
1.2 연구의 범위 및 절차 3
제 2장 예비적 고찰 5
2.1 해체공사 5
2.1.1 해체공법의 분류 5
2.1.2 해체공사의 절차 7
2.1.3 해체공사비의 구성 9
2.2 선행연구 고찰 10
2.3 소 결 14
제 3장 해체공사비 변동 영향요인 도출 및 분석 15
3.1 해체공사비 변동 영향요인 도출 15
3.1.1 문헌 조사를 통한 1차 요인 도출 15
3.1.2 전문가 그룹 인터뷰를 통한 최종 요인 도출 16
3.2 데이터 수집 및 신뢰도 평가 20
3.3 해체공사비 변동 영향요인 분석 23
3.3.1 공정별 해체공사비 변동 영향요인 중요도 23
3.3.2 전체공정과 개별공정의 공사비 변동 영향요인 중요도 비교 33
3.4 소결 41
제 4장 해체공사 현장정보 수집 및 공사비 분석 42
4.1 해체공사 현장정보 수집 42
4.2 현장속성에 따른 공사비 변동 분석 47
4.2.1 가설공사 단위공사비 분석 51
4.2.2 본 구조물 해체 단위공사비 분석 53
4.2.3 해체폐기물 처리 단위공사비 분석 55
4.2.4 전체공정 단위공사비 분석 57
4.3 소 결 59
제 5장 결 론 60
5.1 연구의 결론 60
5.2 연구의 한계 및 향후 연구방향 62
참고문헌 63
부 록 68
- Degree
- Master
- Publisher
- 조선대학교 대학원
- Citation
- 신동욱. (2019). 건축물 해체공사비 영향요인 및 실적공사비 분석 연구.
- Type
- Dissertation
- URI
- https://oak.chosun.ac.kr/handle/2020.oak/13853
http://chosun.dcollection.net/common/orgView/200000267101
-
Appears in Collections:
- General Graduate School > 3. Theses(Master)
- Authorize & License
-
- AuthorizeOpen
- Embargo2019-02-08
- Files in This Item:
-
Items in Repository are protected by copyright, with all rights reserved, unless otherwise indicated.